How a kitchen install works, step by step
Most homeowners want to know one thing: how long will I be without a kitchen? For an average kitchen, fitting itself takes about 3 to 5 working days, but the whole job runs longer once electrics, plastering and worktop templating are included. Here is how it usually goes.
- Planning and design. Measure up, choose a layout and set a budget. Allow roughly 2 to 8 weeks, longer if you are comparing suppliers.
- Survey and measure. A fitter or the retailer checks walls, floors, pipes and electrics. Do this before you order, because a wrong measurement is expensive.
- Order and wait. Made-to-order kitchens can take 2 to 8 weeks to arrive. Check every box on delivery.
- Strip out. The old kitchen comes out, along with old flooring and splashbacks if needed.
- First fix. Electrician, plumber and gas engineer run new cables and pipes. Plastering follows if walls were opened up.
- Flooring. Fit hard flooring before units if it will run under them, or after if it only goes in front.
- Fit the units. Base units are levelled first, then wall units, then doors and handles.
- Worktops. Laminate and wood are cut and fitted on site. Stone and quartz are templated, made off site and fitted a week or two later.
- Second fix. Sink, taps, hob, oven, lighting and sockets are connected and tested.
- Finishing. Splashbacks, painting, cornice and plinths. The fitter fixes any snags.
- Sign-off. Get your electrical certificate and Gas Safe record, plus appliance guarantees.
Tips from the shop floor
- Set up a temporary kitchen with a kettle, microwave and basin in another room.
- Agree the order of trades before day one.
- Keep a buffer. Hidden damp, old pipes and uneven walls are common.